In which process are corrective actions taken to ensure that the management stage remains within tolerance?
In which process are corrective actions taken to ensure that the management stage remains within tolerance?
The correct process for taking corrective actions to ensure that the management stage remains within tolerance is 'Controlling a stage'. This involves assigning work, monitoring progress, dealing with issues, reporting to the project board, and taking any necessary corrective actions to keep the stage within the set tolerances.
17.1 Purpose The purpose of the controlling a stage process is to assign work to be done, monitor such work, deal with issues, report progress to the project board, and take corrective actions to ensure that the management stage remains within tolerance.
Should be D: The process that involves taking corrective actions to ensure that the management stage remains within tolerance is called "Managing a Stage Boundary."