PRINCE2-Foundation Exam - Question 255


In which process are corrective actions taken to ensure that the management stage remains within tolerance?

Show Answer
Correct Answer: C

The correct process for taking corrective actions to ensure that the management stage remains within tolerance is 'Controlling a stage'. This involves assigning work, monitoring progress, dealing with issues, reporting to the project board, and taking any necessary corrective actions to keep the stage within the set tolerances.

Discussion

3 comments
Sign in to comment
ZariniOption: C
Feb 16, 2024

17.1 Purpose The purpose of the controlling a stage process is to assign work to be done, monitor such work, deal with issues, report progress to the project board, and take corrective actions to ensure that the management stage remains within tolerance.

ghjiesis
Apr 12, 2023

Should be D: The process that involves taking corrective actions to ensure that the management stage remains within tolerance is called "Managing a Stage Boundary."

Examcollectorthanos
Nov 12, 2024

C =correct; Why the other options are less suitable: A. Directing a project: This process is about the project board's overall guidance and authorization, not the detailed monitoring and control within a stage. B. Managing product delivery: This process focuses on accepting completed products from teams, not the ongoing monitoring and control of the stage. D. Managing a stage boundary: This process is about the transition between stages, not the day-to-day management within a stage.