Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 11

Which should be funded by a change budget?

    Correct Answer: A

    A change budget is meant to cover the costs associated with implementing changes to a project. An increase in the agreed scope of a project would necessitate additional funds to cover the extra work, resources, and time required. Therefore, an increase in agreed scope should be funded by a change budget.

Discussion
omandeOption: C

Change budget = The money allocated to the change authority available to be spent on authorized requests for change Change authority = A person or group to which the project board may delegate responsibility for the consideration of requests for change or off-specifications. The change authority may be given a change budget and can approve changes within that budget

faileruOption: A

A is the answer as its a change in scope