Which statement about time-driven controls is CORRECT?
Which statement about time-driven controls is CORRECT?
Time-driven controls are used for monitoring the progress of work packages and management stages. These controls involve the use of schedules, timelines, and deadlines to track the progress and ensure that the project is completed within the specified time frame.
Time-driven controls are used for monitoring the progress of work packages and management stages. This statement is correct. Time-driven controls are used for monitoring the progress of work packages and management stages. Time-driven controls involve the use of schedules, timelines, and deadlines to track the progress of the project. This helps to ensure that the project is completed within the specified time frame.