Question 21

Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

    Correct Answer: B

    Follow-on action recommendations should be used to document any uncompleted work that needs to be done to a project product after the project has closed. This ensures there is a clear plan for addressing any outstanding tasks, issues, or risks post-project completion.

Discussion
JasonbahrOption: B

The objective of the closing a project process is to: verify user acceptance of the project's products ensure that the host site is able to support the products when the project is disbanded review the performance of the project against its baselines assess any benefits that have already been realized and update the benefits management approach to include any post-project benefit reviews ensure that provision has been made to address all open issues and risks, with follow-on action recommendations.

peppeOption: B

B is correct

peppeOption: B

correct, "In consultation with the project management team, prepare follow-on action recommendations for the project’s products to include any uncompleted work, issues and risks. There could be separate follow-on action recommendations for each product or distinct user group (e.g. human resources, finance, operations)."

kal5

PM Responsibility