PRINCE2-Foundation Exam - Question 51


What product is used to maintain a record of those who have an interest in the project and their information requirements?

Show Answer
Correct Answer: B

The product used to maintain a record of those who have an interest in the project and their information requirements is the Communication Management Strategy. This document outlines how to communicate internally and externally to meet the project's needs and specifies the target groups and their specific information requirements. The Project Plan outlines the project's objectives, scope, and deliverables. The Project Brief provides an overview of the project, and the Project Product Description defines the final product's technical specifications.

Discussion

1 comment
Sign in to comment
a2d1fd1Option: B
Apr 16, 2024

The Project board and business layer have contact throughout the project which is documented in the communication management approach.