Which role is responsible for focusing on the safety and well-being of the project team?

Show Answer
Correct Answer:

Discussion

4 comments
Sign in to comment
itelessons
Jan 6, 2025

6.2.4.4 Project board

Examcollectorthanos
Nov 16, 2024

C is correct; Here’s why the other options are incorrect: A. Project Executive: Incorrect. The Project Executive focuses on ensuring the project remains aligned with business objectives and provides value for money but does not oversee the safety and well-being of the team directly. B. Project Board: Incorrect. The Project Board is responsible for governance and decision-making at a strategic level, but it delegates day-to-day responsibilities, including team well-being, to the Project Manager. D. Team Manager: Incorrect. While the Team Manager is responsible for delivering specific work packages and managing team activities, the overall responsibility for team well-being lies with the Project Manager, who oversees the project as a whole.

ArisLOption: B
Mar 30, 2025

6.2.4.4 Project board focusing on the safety and well-being of the project team

KjennsetOption: C
May 4, 2025

The correct answer is: C. Project manager Explanation: According to PRINCE2 7, one of the updated responsibilities of the Project Manager is to focus on people management, including: • Safety and well-being of the project team • Supporting a positive working environment • Promoting inclusion and collaboration This is a newer emphasis in PRINCE2 7, reflecting the framework’s increased focus on people and sustainability.