Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 32

Who should act as the communication channel between a project and corporate or programme management?

    Correct Answer: A

    The Project Board should act as the communication channel between a project and corporate or programme management. They have the authority and responsibility to provide direction and support to the Project Manager, ensuring the project's alignment with organizational objectives and facilitating smooth communication with higher management levels.

Discussion
IsabautOption: A

Project Board is correct

FireyOption: A

The project board also acts as a communication channel or interface with corporate management.