Which type of issue should be raised if a quality review finds that a product does not meet the criteria in the product description?

    Correct Answer: B

    If a quality review finds that a product does not meet the criteria in the product description, the appropriate type of issue to raise is an off-specification. This is a situation where something that should be provided by the project is either not present or does not meet its intended specifications. Off-specification can include missing products or products that fail to meet the established criteria.

Discussion
Martin77Option: B

This is wrong. I think the correct answer is B. off-specification according to the definitions in the Prince2 manual. off-specification (matches the question) Something that should be provided by the project, but currently is not (or is forecast not to be). It might be a missing product or a product not meeting its specifications. It is one type of issue. request for change A proposal for a change to a baseline. It is a type of issue. problem A type of issue (other than a request for change or off-specification) that the project manager needs to resolve or escalate. Also known as a concern.

AliSamiOption: B

B is the correct answer

NugiOption: B

Definitively the answer is B. Reference: Off-Specification is something that should be provided by the project, but currently is not (or is forecast not to be). It might be a missing product or a product not meeting its specifications.

Ppp333Option: B

A.8.2 Off-specifications Listing any missing products or products that do not meet the original requirements, and confirmation of any concessions granted

jj0097Option: B

B is good