PRINCE2-Practitioner Exam - Question 121


MANAGING A STAGE BOUNDARY -

The ABC Company trainers have been accredited and the course booking procedures have been amended. The 'managing a stage boundary' process is taking place at the end of stage 3.

Which activity should occur during the 'update the business case' activity?

Show Answer
Correct Answer: C

During the 'update the business case' activity, it is essential to review whether the possible sales of the training course to external companies are likely to cover the project costs. This involves assessing the financial viability and business justification of the project to ensure it is still a sound investment and beneficial to continue. Therefore, option C is the most appropriate as it directly pertains to assessing the financial implications and ensuring the project remains viable.

Discussion

2 comments
Sign in to comment
ravi_awsOption: C
Oct 1, 2023

In the scenario, reviewing whether the possible sales of the training course to external companies are likely to cover the project costs falls under this activity. This is because it involves assessing the financial viability of the project, which is a key aspect of updating the Business Case2. So, option C) is most appropriate for this situation.

ravi_aws
Oct 1, 2023

C is the best answer

ManikRoyOption: C
Oct 8, 2023

Option C is correct as it reviews the business justification of the project to understand if the project is still cost effective i.e. if the project is still desirable.

ManikRoy
Oct 9, 2023

refer 19.4.3 Examine & review 2nd point the impact of approved changes as these may affect the projected benefits

ManikRoy
Oct 9, 2023

It also does mention to review and examine the Project Plan but doesn't mention if it needs to be updated in this process/activity. Review & Examine - the project plan to see whether the final implementation date of the project has changed (to earlier or later), which might affect some or all of the projected benefits the project plan to see whether the cost of delivering the project's products has changed, which may affect the cost-benefit analysis