Which statement about the Directing a Project process is true?
Which statement about the Directing a Project process is true?
The statement that 'provides a mechanism for the Project Board to assure that there is continued business justification' is true about the Directing a Project process. This process focuses on the responsibilities and decisions of the Project Board, including ensuring that the project remains viable and aligns with business objectives.
This one is tricky. D is wrong because the directing a project process starts on completion of the starting up a project process and is triggered by the request(!), not completion, to initiate a project. Therefore A is correct: The directing a project process provides a mechanism for the project board to meet its responsibility for ensuring that there is continued business justification without being overburdened by project activity.
The directing a project process covers the activities of the project board and is not concerned with the day-today activities of the project manager.
A is the correct answer.