Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 33

Which statement about the Directing a Project process is true?

    Correct Answer: A

    The statement that 'provides a mechanism for the Project Board to assure that there is continued business justification' is true about the Directing a Project process. This process focuses on the responsibilities and decisions of the Project Board, including ensuring that the project remains viable and aligns with business objectives.

Discussion
JasonbahrOption: A

This one is tricky. D is wrong because the directing a project process starts on completion of the starting up a project process and is triggered by the request(!), not completion, to initiate a project. Therefore A is correct: The directing a project process provides a mechanism for the project board to meet its responsibility for ensuring that there is continued business justification without being overburdened by project activity.

[Removed]Option: A

The directing a project process covers the activities of the project board and is not concerned with the day-today activities of the project manager.

a2d1fd1Option: A

A is the correct answer.