Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 36

Which is NOT a purpose of the Initiating a Project process?

    Correct Answer: D

    The purpose of the Initiating a Project process includes enabling a Project Board decision about the commitment of resources to a project, enabling an organization to understand the work that needs to be done to deliver a project’s products before a project is approved, and establishing solid foundations for a project. The statement 'Enable the Project Board to decide whether it is worthwhile to initiate a project' pertains more to the Starting up a Project process, not the Initiating a Project process. Therefore, it is not a purpose of the Initiating a Project process.

Discussion
renzaOption: D

The answer is D These are key words for each process: starting up a project: deciding whether the project is(viable and worthwhile)? Initiating a project: establish (solid foundations) for the project.

OmaiOption: D

The answer is D The purpose of the initiating a project process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project product before committing to a significant spend.

mk_dyn365Option: A

Answer Should be A. If anyone can confirm, will be grateful. TIA

Toni85

D is a purpose of 12. Start-up of a Proyect

OridanDesta

I agree to this statement

a2d1fd1Option: D

D is not a purpose of the initiation process.

majoy010190Option: D

D is the answer. The statement includes the word “Initiate” not realize. Why do you suppose that the correct answer should be A ?

ArifNazinOption: D

Cannot be A, as one of the objective of initiation stage is to allow PB to make decision on the resources.

hazrdzOption: A

Answer should be A