Which is NOT a purpose of the Initiating a Project process?
Which is NOT a purpose of the Initiating a Project process?
The purpose of the Initiating a Project process includes enabling a Project Board decision about the commitment of resources to a project, enabling an organization to understand the work that needs to be done to deliver a project’s products before a project is approved, and establishing solid foundations for a project. The statement 'Enable the Project Board to decide whether it is worthwhile to initiate a project' pertains more to the Starting up a Project process, not the Initiating a Project process. Therefore, it is not a purpose of the Initiating a Project process.
The answer is D These are key words for each process: starting up a project: deciding whether the project is(viable and worthwhile)? Initiating a project: establish (solid foundations) for the project.
The answer is D The purpose of the initiating a project process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project product before committing to a significant spend.
Answer Should be A. If anyone can confirm, will be grateful. TIA
D is a purpose of 12. Start-up of a Proyect
I agree to this statement
D is not a purpose of the initiation process.
D is the answer. The statement includes the word “Initiate” not realize. Why do you suppose that the correct answer should be A ?
Cannot be A, as one of the objective of initiation stage is to allow PB to make decision on the resources.
Answer should be A