PRINCE2-Foundation Exam QuestionsBrowse all questions from this exam

PRINCE2-Foundation Exam - Question 36


Which is NOT a purpose of the Initiating a Project process?

Show Answer
Correct Answer: D

The purpose of the Initiating a Project process includes enabling a Project Board decision about the commitment of resources to a project, enabling an organization to understand the work that needs to be done to deliver a project’s products before a project is approved, and establishing solid foundations for a project. The statement 'Enable the Project Board to decide whether it is worthwhile to initiate a project' pertains more to the Starting up a Project process, not the Initiating a Project process. Therefore, it is not a purpose of the Initiating a Project process.

Discussion

7 comments
Sign in to comment
renzaOption: D
Feb 25, 2023

The answer is D These are key words for each process: starting up a project: deciding whether the project is(viable and worthwhile)? Initiating a project: establish (solid foundations) for the project.

mk_dyn365Option: A
Dec 6, 2021

Answer Should be A. If anyone can confirm, will be grateful. TIA

Toni85
Apr 22, 2022

D is a purpose of 12. Start-up of a Proyect

OridanDesta
Jun 28, 2022

I agree to this statement

OmaiOption: D
Mar 10, 2023

The answer is D The purpose of the initiating a project process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project product before committing to a significant spend.

hazrdzOption: A
Aug 8, 2022

Answer should be A

ArifNazinOption: D
Feb 3, 2023

Cannot be A, as one of the objective of initiation stage is to allow PB to make decision on the resources.

majoy010190Option: D
Oct 14, 2023

D is the answer. The statement includes the word “Initiate” not realize. Why do you suppose that the correct answer should be A ?

a2d1fd1Option: D
Apr 15, 2024

D is not a purpose of the initiation process.