PRINCE2-Foundation Exam - Question 210


Which process plans the activities of the 'closing a project' process?

Show Answer
Correct Answer: A,B

The process that plans the activities of the 'closing a project' process is 'Managing a stage boundary'. The 'Managing a stage boundary' process involves preparing for the end of a stage and planning for the next one. This includes planning for the activities necessary to close the project properly. The 'closing a project' process itself is about executing the planned activities, not planning them.

Discussion

5 comments
Sign in to comment
themvp9Option: A
Feb 2, 2022

I would say A: The activities within the closing a project process are project-manageroriented and are to: prepare planned closure prepare premature closure hand over products evaluate the project recommend project closure.

lucafrancoOption: B
Dec 29, 2021

I think that this is a tricky question. The correct answer its B 'Manage a stage boundry'. The question ask which process PLANS the activities about closing the project and not where those activity are executed.

AliSamiOption: B
Apr 24, 2022

B is the correct answer

MyName_Option: A
Jul 1, 2023

The correct answer is A. At the end of the last stage, there are no more no more products, hence no more stages to manage. The correct answer is therefore option A.

bes_iOption: B
Jul 20, 2024

B. Managing a Stage Boundary The 'Managing a Stage Boundary' process involves preparing for the end of a stage and planning for the next one, including the activities necessary for closing the project. This process ensures that all the necessary steps are taken to finalize and close the project properly, including addressing any outstanding issues and ensuring that all deliverables meet the required standards.