Question 129

Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

    Correct Answer: D

    In the 'starting up a project' process within PRINCE2 methodology, the Project Brief is created to define and confirm the scope of the project. It acts as a short description of what the project is to achieve, including the project objectives, scope, constraints, and assumptions. This ensures that everyone involved has a clear and agreed understanding of the project objectives before progressing to the initiation stage.

Discussion
GetRajOption: D

Option D seems to be correct

AgnesMOption: D

According to A.19.2 of Prince 2 project brief provides project definition which constrains of: project scope and exclusions, contraints and assumptions.

LenlenlenOption: D

Should be D

Martin77Option: D

D - Project Brief is correct

JasonbahrOption: D

I concur with D

DS001Option: D

I agree, Project brief describes about the scope of the project.

sohrabianiOption: D

D Seems to be correct

GLKTYIOption: D

Initiation stage plan, not defining scope but plan activity during initiation stage and provide project board with elaborate outlined business case in project brief. It should be D