Which product is created in the 'starting up a project' process to define and confirm the scope of the project?
Which product is created in the 'starting up a project' process to define and confirm the scope of the project?
In the 'starting up a project' process within PRINCE2 methodology, the Project Brief is created to define and confirm the scope of the project. It acts as a short description of what the project is to achieve, including the project objectives, scope, constraints, and assumptions. This ensures that everyone involved has a clear and agreed understanding of the project objectives before progressing to the initiation stage.
Option D seems to be correct
According to A.19.2 of Prince 2 project brief provides project definition which constrains of: project scope and exclusions, contraints and assumptions.
Should be D
D - Project Brief is correct
I concur with D
I agree, Project brief describes about the scope of the project.
D Seems to be correct
Initiation stage plan, not defining scope but plan activity during initiation stage and provide project board with elaborate outlined business case in project brief. It should be D