Question 12

Which of the following activities could trigger the production of an exception plan?

    Correct Answer: B

    Giving ad hoc direction can trigger the production of an exception plan because it often involves making adjustments or special directives that address unexpected issues or deviations from the project plan. This scenario fits the context where an exception plan would be necessary to realign the project with its objectives after encountering unexpected changes.

Discussion
ravi_awsOption: C

C. Escalating a project issue

ManikRoyOption: B

Rectifying my previous answer, As per Figure 15.1 in the 'Directing a project process', 'Give Adhoc Direction' can lead to 'Exception plan request'

ManikRoyOption: C

Correct option should be C. D can not be the correct answer as the end stage reports is followed by and exception report.

ManikRoy

Rectifying my previous answer, As per Figure 15.1 in the 'Directing a project process', 'Give Adhoc Direction' can lead to 'Exception plan request'

VSLMOption: C

C is the right answer.

Old_JediOption: C

I think C is the answer; an exception plan is created "during" a stage to address a significant deviation. In that context, a significant issue that requires escalation justifies the need for an exception plan to be created.

ChivasaOption: B

The end stage report can be made before an exception plan depending on where the stage is, it is however the board under the ad hoc direction that instructs the PM to create the exception plan so the answe is B

georgio1974Option: D

19.4.4, exception plan requires and end stage report