Question 204

Without a Risk Register how can project risks, the progress of risk actions taken to date and the current status of residual risks be measured?

    Correct Answer: C

    In a simple project, the Project Initiation Documentation (PID) should contain a register for recording risk information and monitoring project risks throughout the delivery stages. This ensures that all risks, alongside the progress of risk actions taken to date and the current status of residual risks, are systematically tracked and managed. A register incorporated within the PID allows for a centralized and organized method to handle this critical information throughout the project's lifecycle.

Discussion
ravi_awsOption: C

C. In a simple project, the Project Initiation Documentation (PID) should contain a register for recording risk information and monitoring project risks throughout the delivery stages. The register will now be added to the PID.