Question 12

Which is the Issue Register NOT used for?

    Correct Answer: C

    The Issue Register is not used to capture any threats or opportunities that might have an impact on a stage. This activity is covered by the Risk Register, which is specially designed to handle risks, including both threats and opportunities, in a project management context.

Discussion
CoffeeODOption: C

C refers to the Risk Registrar

IsabautOption: C

Correct

missmanouOption: C

C is correct