Which is the Issue Register NOT used for?
Which is the Issue Register NOT used for?
The Issue Register is not used to capture any threats or opportunities that might have an impact on a stage. This activity is covered by the Risk Register, which is specially designed to handle risks, including both threats and opportunities, in a project management context.
C refers to the Risk Registrar
C is correct
Correct
problems identified when authorizing a Work Package would typically be handled through the Work Package documentation and the Checkpoint Reports rather than the Issue Register.
Problems identified when authorizing a Work Package are typically dealt with before the Work Package is authorized. Any such problems would need to be resolved or escalated before the Work Package proceeds. These are more relevant to Work Package management or quality controls, not the Issue Register directly.