Which product should show that if anybody has any remaining resource costs to be charged to the project, they should ensure this is done by 10 November?
Which product should show that if anybody has any remaining resource costs to be charged to the project, they should ensure this is done by 10 November?
The correct product to convey instructions for handling any remaining resource costs to be charged to the project by a specific deadline, such as 10 November, is the Project closure notification. This document formally notifies stakeholders of the project’s closure and includes important final administrative tasks, such as ensuring all resource costs are accounted for and allocated appropriately.
option D is the correct choice, as the Project closure notification should include instructions for charging any remaining resource costs before the given deadline of 10 November