PRINCE2-Foundation Exam - Question 113


Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

Show Answer
Correct Answer: D

The process that provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification is Managing a Stage Boundary. This process is essential as it involves assessing the achievements of the current stage, planning for the next stage, and ensuring that the justification for the project remains valid.

Discussion

2 comments
Sign in to comment
Firey
Jul 23, 2024

The process that provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification is D. Managing a Stage Boundary.

Nabin55555hhhjjOption: D
Feb 10, 2024

D is answer