Question 109

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

    Correct Answer: D

    The process that provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification is Managing a Stage Boundary. This process is essential as it involves assessing the achievements of the current stage, planning for the next stage, and ensuring that the justification for the project remains valid.

Discussion
FireyOption: D

The process that provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification is D. Managing a Stage Boundary.

Nabin55555hhhjjOption: D

D is answer