PRINCE2-Foundation Exam QuestionsBrowse all questions from this exam

PRINCE2-Foundation Exam - Question 27


What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

Show Answer
Correct Answer: B

The process used by the Project Manager to maintain focus on the delivery of a stage's products within agreed tolerances is 'Controlling a Stage'. This process encompasses monitoring and controlling the progress of the project against the project plan, ensuring that defined quality criteria are met, and making sure that projects remain within the set tolerances for time, cost, quality, scope, risk, and benefits, which helps in maintaining focus on product delivery.

Discussion

2 comments
Sign in to comment
ghjiesisOption: C
Apr 13, 2023

Should be C: The process used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances is called "Managing Stage Boundaries." This process is part of the PRINCE2 (Projects in Controlled Environments) methodology, which is a widely used project management framework.

johnny1001
Apr 15, 2023

Never heard of it.

d1acd9cOption: C
Jan 22, 2024

Answer is C