Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 27

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

    Correct Answer: B

    The process used by the Project Manager to maintain focus on the delivery of a stage's products within agreed tolerances is 'Controlling a Stage'. This process encompasses monitoring and controlling the progress of the project against the project plan, ensuring that defined quality criteria are met, and making sure that projects remain within the set tolerances for time, cost, quality, scope, risk, and benefits, which helps in maintaining focus on product delivery.

Discussion
d1acd9cOption: C

Answer is C

ghjiesisOption: C

Should be C: The process used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances is called "Managing Stage Boundaries." This process is part of the PRINCE2 (Projects in Controlled Environments) methodology, which is a widely used project management framework.

johnny1001

Never heard of it.