Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 29

Which is a purpose of the 'directing a project' process?

    Correct Answer: C

    The purpose of the 'directing a project' process is to enable the project board to be accountable for the project's success by making key decisions and exercising overall control, while delegating day-to-day management of the project to the project manager. This ensures that the project board can focus on strategic decision-making and project governance, and the project manager can handle the practical, day-to-day tasks involved in managing the project.

Discussion
Annie7799666Option: C

The purpose of the Directing a Project process is to enable the Project Board to be accountable for the project by making key decisions, to have overall control and "delegate day-to-day management of the project to the Project Manager."