Question 173

What problem may occur if projects are not aligned with corporate business strategy?

    Correct Answer: C

    If projects are not aligned with corporate business strategy, the objectives of different projects may overlap. Misalignment can lead to duplications and inconsistencies among project goals, causing inefficiencies and conflicts within the organization's overall project portfolio.

Discussion
GetRajOption: C

Option C is correct

Martin77Option: D

D is the correct answer: "corporate, programme management or customer standards These are overarching standards to which the project must adhere. They will influence the four project approaches (communication management, change control, quality management and risk management) and the project controls." reference prince2 guide glossary on corporate, programme management or customer standards

HelgeFFMOption: C

I would also say C

omandeOption: C

Textbook pp. 21: "Poor alignment with corporate, programme management or customer strategies can also result in organizations having a portfolio of projects that have mutually inconsistent or duplicated objectives."

RznNsrOption: B

I hope its B