Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 28

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

    Correct Answer: C

    A Project Manager defines the time and cost tolerances for the work to be done by a Team Manager in a Work Package. This is because a Work Package is a set of information about one or more required products collated by the Project Manager to pass responsibility for delivery to a Team Manager. It outlines what needs to be delivered, the constraints, standards to be applied, and, importantly, the tolerances within which the Team Manager must work.

Discussion
peppeOption: C

C is correct the words " work to be done " are crucials

peppeOption: C

CORRECT :"The team manager has control for a work package, but only within the work package tolerances agreed with the project manager. During execution of the work package, if any forecasts indicate that it is likely that the agreed tolerances will be exceeded, then the deviation should be referred to the project manager by the team manager in order to get a decision on corrective action. This would be done by raising an issue.