PRINCE2-Foundation Exam QuestionsBrowse all questions from this exam

PRINCE2-Foundation Exam - Question 159


According to the 'tailor to suit the project' principle, what is the basis for effective project management?

Show Answer
Correct Answer: D

The 'tailor to suit the project' principle in effective project management emphasizes that the project management method must be adapted to align with the project's environment. This means tailoring the methodology to fit the specific circumstances and requirements of the project’s operational context, making it most suitable and effective for managing the particular project.

Discussion

7 comments
Sign in to comment
mazzantiemanueleOption: C
Mar 25, 2022

Shoul be C? Pag. 27 of the official guide Tailoring requires the project board and the project manager to make proactive choices and decisions on how PRINCE2 will be applied. When tailoring PRINCE2, it is important to remember that effective project management requires information (not necessarily documents) and decisions (not necessarily meetings).

King_LapsOption: C
Oct 31, 2022

the correct answer is C

sdoukkalOption: C
Mar 9, 2023

I was expecting C to be the right answer .

sdoukkalOption: C
Mar 9, 2023

To me correct answer is C

majoy010190Option: D
Oct 15, 2023

Why D should be the correct answer?

omandeOption: C
Nov 15, 2023

P.27 of the Textbook indicates that one of the purpose of tailoring should be that "the project management method used is appropriate to the project (e.g. aligning the method with the business processes that may govern and support the project, such as human resources, finance and procurement)". However, project is different from the project's environment. I would thus also go for C.

TaiHOption: C
Jan 17, 2024

should be C, same reasons others have mentioned already