Which management product do the Project Board use to decide whether to authorize initiation?
Which management product do the Project Board use to decide whether to authorize initiation?
The Project Board uses the Project Brief to decide whether to authorize initiation. The Project Brief provides a summary of the project, including its objectives, scope, and overall approach, which allows the Project Board to make an informed decision about whether to proceed with the project initiation.
A - Project Brief (see Figure 15.2)
This should be this PID
I believe PID is used to authorize the project, not to authorize initiation