Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 98

Which management product do the Project Board use to decide whether to authorize initiation?

    Correct Answer: A

    The Project Board uses the Project Brief to decide whether to authorize initiation. The Project Brief provides a summary of the project, including its objectives, scope, and overall approach, which allows the Project Board to make an informed decision about whether to proceed with the project initiation.

Discussion
timedoutOption: A

A - Project Brief (see Figure 15.2)

AdeeyOption: C

This should be this PID

Andreas1975

I believe PID is used to authorize the project, not to authorize initiation