PRINCE2-Practitioner Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Exam - Question 61


If the Project Board are too busy to authorize all change requests themselves they can appoint?

Show Answer
Correct Answer: A

If the Project Board is too busy to authorize all change requests themselves, they can appoint a Change Authority. The Change Authority is a designated entity or individual given the responsibility to consider and approve changes, ensuring that the process is streamlined and efficient.

Discussion

6 comments
Sign in to comment
CilubaOption: A
Dec 18, 2020

Should be A

ChickeyOption: A
Jul 1, 2020

Answer should be A - see brochure page 142, 11.3.5

GSD547Option: A
Apr 18, 2022

Answer is A - clearly states this in delegating to a Change Authority (Ch 11.3.5).

SantiagoAregentinaOption: A
Sep 9, 2023

A. Ref 11.3.5

ravi_awsOption: A
Oct 1, 2023

A Change Authority

Capstein_1Option: C
Feb 28, 2024

Change Authority can be called Change Committee.