Question 61

If the Project Board are too busy to authorize all change requests themselves they can appoint?

    Correct Answer: A

    If the Project Board is too busy to authorize all change requests themselves, they can appoint a Change Authority. The Change Authority is a designated entity or individual given the responsibility to consider and approve changes, ensuring that the process is streamlined and efficient.

Discussion
CilubaOption: A

Should be A

ChickeyOption: A

Answer should be A - see brochure page 142, 11.3.5

GSD547Option: A

Answer is A - clearly states this in delegating to a Change Authority (Ch 11.3.5).

SantiagoAregentinaOption: A

A. Ref 11.3.5

Capstein_1Option: C

Change Authority can be called Change Committee.

ravi_awsOption: A

A Change Authority