There is no mention of any Stage Plans, yet there are two further stages proposed. How will this be resolved?
There is no mention of any Stage Plans, yet there are two further stages proposed. How will this be resolved?
It is appropriate for the Calendar project to be run as two further stages since there is a key decision to be made at the end of stage 2. This naturally divides the project into distinct phases requiring their respective Stage Plans, ensuring structured management and control throughout its lifecycle.
A. It is appropriate for the Calendar project to be run as two further stages as there is a key decision to be made at the end of stage 2. Stage Plans will be produced.