Question 131

Which process is used to define how baselines will be established and controlled?

    Correct Answer: C

    The process used to define how baselines will be established and controlled is 'Initiating a project.' During this process, the groundwork is laid for how various aspects of the project, including baselines, will be managed. This involves setting up the scope of the project, planning how and when deliverables will be produced, and determining how project progress will be monitored and controlled, which includes the establishment and control of baselines.

Discussion
GLKTYIOption: C

It should be C, starting up project not defining baseline but define and confirm initial scope in project brieft

GetRajOption: C

Option C seems to be correct

Risto83Option: C

C 16.2: The objective of the initiating a project process is to ensure that there is a common understanding of: ● the reasons for doing the project, the benefits expected and the associated risks ● the scope of what is to be done and the products to be delivered ● how and when the project’s products will be delivered and at what cost ● who is to be involved in the project decision-making ● how the quality required will be achieved ● how baselines will be established and controlled ● how risks, issues and changes will be identified, assessed and controlled ● how progress will be monitored and controlled ● who needs information, in what format and at what time ● how the corporate, programme management or customer method will be tailored to suit the project.

Martin77Option: C

C - Initiating a Project. One of the objectives of this process is to define how baselines will be established and controlled . Reference - Prince2 manual, 16.2

TesteurtestOption: C

Starting up is about defining what customer needs, Init the project is about defining how it will be done and provide documents https://prince2.wiki/processes/initiating-a-project/

Becks89Option: D

The Starting up project uses Baseline Management Products, one of them is the Project Brief. Therefore D is the correct option.

AgnesMOption: C

Change control approach is defined during Initiating a project process, therefore option C seems to be correct.

sohrabianiOption: C

I think C should be correct - In SU we do not do anything about Baselines since the initiation is not authorized by DP yet

SGN63Option: C

C is the correct answer

AnapellicerOption: C

C should be the correct answer

renzaOption: C

c is the correct answer

Trikuta_KairaOption: C

Answer should be "C" (Initiating a Project) as "how baselines will be established and controlled" is the objective of "Initiating a Project" process.

peppeOption: C

C is correct

MehanOption: B

option B is correct because PID is produced in the directing stage. PID defines the project and forms the basis for the managing and assessment of overall project success. Ref.A.20

DS001

PID is created in Initiating a project process