Which describes an off-specification?
Which describes an off-specification?
An off-specification refers to a situation where a product or deliverable deviates from its specified requirements or quality criteria. This includes cases where more (or fewer) products are produced than what was originally defined. Therefore, the production of more than the defined quantity of a specialist product fits the description of an off-specification.
According to A.8.2 Composition, where mentioned about Off-specifications: "Listing any missing products or products that do not meet the original requirements, and confirmation of any concessions granted" in a glossary also given a description for off-specification - Something that should be provided by the project, but currently is not (or is forecast not to be) . It might be a missing product or a product not meeting its specifications. It looks A is a correct answer
Option D seems to be correct.
I think A is correct
D. The production of more than the defined quantity of a specialist product In PRINCE2, an off-specification refers to a situation where a product or deliverable deviates from its specified requirements or quality criteria. This includes cases where more (or fewer) products are produced than what was originally defined or where the products do not meet the agreed-upon standards.
How many correct answer? If two answers, it seems like D and A.
A.9.2 (Prince2 guide) Off-specifications Listing any missing products or products that do not meet the original requirements, and confirmation of any concessions granted
Off-specification doesn't talk about 'interdependency between products'
I thin both A & D are correct since the producing the product more than required number also can be categorized as Off-Specification