Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 55

Who is responsible for reviewing the risk management practices to ensure they are in line with the project's risk management strategy?

    Correct Answer: D

    The Project Assurance role is responsible for ensuring that the project's risk management practices align with the project's risk management strategy. Project Assurance provides an independent check on all aspects of the project's performance, ensuring that risks are being adequately managed according to the approved plans and strategies.

Discussion
PrincessOfHessOption: D

It is D (10.2.1)