A single work package has been created for the products of stage 2 and a team manager appointed for the whole work package. The team manager has split the work package into multiple smaller work packages for each product to be delivered in stage 2. The 'managing product delivery' process activities have been tailored so that the lower-level team managers report to the higher-level team manager.
Is this an appropriate application of the 'managing product delivery' process, and why?