Question 269

The 'e-learning course' is being delivered by an external consultancy. The consultancy completed work on the 'accredited e-learning course' during stage 3.

However, the 'delivered pilot courses' includes piloting of the e-learning course. As a result, the external consultancy is required to do further work as part of the

'finalized materials'.

When should the external consultancy close their project, and why?

    Correct Answer: D

    The external consultancy should close their project when the 'finalized materials' have been approved because they should complete all their contractual activities before project closure. This ensures that the deliverables have met the required standards and fulfill the contract obligations.

Discussion
ravi_awsOption: D

The external consultancy should close their project when the ‘finalized materials’ have been approved. This is because the external consultancy’s business case is separate from ABC Company’s business case, and they should complete their contractual activities before closing. So, the correct answer would be: D