PRINCE2-Practitioner Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Exam - Question 304


Which 2 statements explain why the Marketing Director should be appointed as a Senior User for this project?

Show Answer
Correct Answer: AC

The Marketing Director should be appointed as a Senior User for this project because she can represent the Marketing department, ensuring that their needs and perspectives are considered. Additionally, the Marketing department will help to deliver the benefits of this project, highlighting the importance of her role in the eventual success of the project.

Discussion

2 comments
Sign in to comment
ravi_awsOptions: CD
Oct 8, 2023

Statement C shows that the Marketing department, which she leads, will be crucial in delivering the project’s benefits. Statement D indicates that the project is funded from her department’s budget, which means she has a vested interest in ensuring the project’s success. So C AND D

Terry007Options: CD
Feb 3, 2024

We all know that she can represent the marketing department , which is obvious but if you had to choose between A and D , where option D relates to funding , i think its a stronger choice between the 2, there C and D.