Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 50

Which does the Executive need to ensure is in place before the project is initiated?

    Correct Answer: B

    Before a project is initiated, the Executive needs to ensure there is a clear understanding of how the project will contribute to corporate objectives. This ensures that the project aligns with the organizational goals and justifies the investment of resources and time. Without this understanding, the project may lack direction and fail to deliver value to the organization.

Discussion
mattersOption: A

The Project Board has to "Verify that the outline business case demonstrates a viable project." Ref 15.4.1 authorize Initiation.