Question 22

Which is an objective of the 'closing a project' process?

    Correct Answer: D

    The objective of the 'closing a project' process is to assess the benefits that have already been realized. During this final phase of a project, it's crucial to evaluate the outcomes and benefits achieved to ensure that the project has met its goals and to identify any lessons learned. This helps in updating the benefits management approach and planning any post-project benefit reviews. Ensuring delivery within set tolerances is typically an objective of project execution, not the closing phase.

Discussion
lucafrancoOption: D

Correct answer shold be D: 20.2 assess any benefits that have already been realized and update the benefits management approach to include any post-project benefit reviews

IsabautOption: D

D correct

Annie7799666Option: D

Answer is D. The objectives of the Closing a Project process are to: Verify user acceptance of the project’s products. Ensure that products can be supported after the project is disbanded. Review the performance of the project. This is done by comparing the project to the baselined documents. Assess the benefits already realized and plan review of benefits that will be realized after the project is complete. Address open issues and risks with a follow-up on action recommendations.

jan_dOption: D

The provided reference does not justify B and it does not make sense logically either. D should be correct.

hazrdzOption: D

Correct is D

mazzantiemanueleOption: D

Correct answer shold be D

AdrienneOption: D

D - Assess the benefits already realized and plan review of benefits that will be realized after the project is complete

skshah47Option: D

D is correct

SGN63Option: D

D is the right answer

renzaOption: D

D is the right answer

as055bOption: D

I would say D - Assess the benefits already realized and plan review of benefits that will be realized after the project is complete.

KeanoDOption: D

D is correct

OridanDestaOption: D

D is correct

a2d1fd1Option: D

D is the correct answer not B

AngeloCOption: D

An objective of the Closing a project is to assess the benefits already realized and plan review of benefits that will be realized after the project is complete (https://prince2.wiki/processes/closing-a-project/) The correct answer is D

mr_alokOption: D

D is correct Not sure why the answer has not been corrected yet