PRINCE2-Foundation Exam QuestionsBrowse all questions from this exam

PRINCE2-Foundation Exam - Question 22


Which is an objective of the 'closing a project' process?

Show Answer
Correct Answer: D

The objective of the 'closing a project' process is to assess the benefits that have already been realized. During this final phase of a project, it's crucial to evaluate the outcomes and benefits achieved to ensure that the project has met its goals and to identify any lessons learned. This helps in updating the benefits management approach and planning any post-project benefit reviews. Ensuring delivery within set tolerances is typically an objective of project execution, not the closing phase.

Discussion

16 comments
Sign in to comment
lucafrancoOption: D
Dec 26, 2021

Correct answer shold be D: 20.2 assess any benefits that have already been realized and update the benefits management approach to include any post-project benefit reviews

mazzantiemanueleOption: D
Mar 21, 2022

Correct answer shold be D

hazrdzOption: D
Apr 4, 2022

Correct is D

jan_dOption: D
Apr 6, 2022

The provided reference does not justify B and it does not make sense logically either. D should be correct.

Annie7799666Option: D
May 14, 2022

Answer is D. The objectives of the Closing a Project process are to: Verify user acceptance of the project’s products. Ensure that products can be supported after the project is disbanded. Review the performance of the project. This is done by comparing the project to the baselined documents. Assess the benefits already realized and plan review of benefits that will be realized after the project is complete. Address open issues and risks with a follow-up on action recommendations.

IsabautOption: D
May 30, 2022

D correct

OridanDestaOption: D
Jun 28, 2022

D is correct

KeanoDOption: D
Aug 29, 2022

D is correct

as055bOption: D
Feb 15, 2023

I would say D - Assess the benefits already realized and plan review of benefits that will be realized after the project is complete.

renzaOption: D
Feb 25, 2023

D is the right answer

SGN63Option: D
Mar 4, 2023

D is the right answer

skshah47Option: D
Mar 9, 2023

D is correct

AdrienneOption: D
Sep 18, 2023

D - Assess the benefits already realized and plan review of benefits that will be realized after the project is complete

mr_alokOption: D
Mar 20, 2023

D is correct Not sure why the answer has not been corrected yet

AngeloCOption: D
Jan 6, 2024

An objective of the Closing a project is to assess the benefits already realized and plan review of benefits that will be realized after the project is complete (https://prince2.wiki/processes/closing-a-project/) The correct answer is D

a2d1fd1Option: D
Apr 11, 2024

D is the correct answer not B