Which is a minimum requirement for applying the 'progress' theme?

Show Answer
Correct Answer: D

Producing highlight and end stage reports is a minimum requirement for applying the 'progress' theme in PRINCE2 methodology. Highlight reports are produced at regular intervals to summarize the project's status, including progress against the plan, issues, risks, and any changes. End stage reports are produced at the end of each stage to summarize outcomes, issues, risks, and changes during that stage.

Discussion

6 comments
Sign in to comment
AnapellicerOption: D
Mar 9, 2023

D is the correct answer. Producing highlight and end stage reports is a minimum requirement for applying the 'progress' theme in PRINCE2 methodology. The highlight report is produced at regular intervals (usually weekly) and summarizes the status of the project, including progress against the plan, issues and risks, and any changes to the plan. The end stage report is produced at the end of each stage and summarizes the outcomes of the stage, including any issues, risks, or changes that occurred during the stage. Option C (To manage by exception against tolerances set for time and cost) is an important consideration for the 'manage by exception' principle, but it is not a minimum requirement for the 'progress' theme.

mr_alokOption: C
Mar 22, 2023

The correct answer is C Set tolerances and be managed by exceptions is minimum requirement

CVR14
Mar 23, 2023

Are these questions still valid to use on the PeopleCert exam in 2023?

RznNsrOption: D
Aug 19, 2023

D is the correct answer. Producing highlight and end stage reports is a minimum

TesteurtestOption: B
Aug 21, 2023

The whole point about "progress" is measuring it. By recording the event and achieved work. Other important items are Authority delegation, have a good sequence/stages, reporting and managing by exception. But firdst, you have to measure progress (B.)

omandeOption: C
Nov 15, 2023

Textbook 12.2: To be following PRINCE2, a project must, as a minimum "set tolerances and be managed by exception against these tolerances (PRINCE2’s manage by exception principle)"