PRINCE2-Foundation Exam QuestionsBrowse all questions from this exam

PRINCE2-Foundation Exam - Question 194


Which is a minimum requirement for applying the change theme?

Show Answer
Correct Answer: A

The minimum requirement for applying the change theme according to PRINCE2 is to identify whether an issue affects the continuation of the project. This encompasses the principle of continued business justification, which ensures that any identified issues are evaluated for their potential impact on the project's viability.

Discussion

6 comments
Sign in to comment
MehanOption: A
Jan 16, 2021

The purpose of the change theme is to identify, ASESS, and control any potential and approved changes to the project baselines. A is Corretct

KianaOption: A
Jul 31, 2020

Definitely B is the wrong answer it’s A

JimethOption: A
Jul 31, 2020

It's A

Mehan
Jan 16, 2021

The purpose of the change theme is to identify, ASESS, and control any potential and approved changes to the project baselines.

NugiOption: A
Jul 4, 2021

Definitely A. Reference: To be following PRINCE2, a project must, as a minimum: ● define its change control approach. This approach must minimally cover: ● how issues are identified and managed ● assessing whether identified issues might have a material impact on the business justification of the project (PRINCE2’s continued business justification principle)

costin31Option: A
Mar 16, 2024

It is A!