Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 194

Which is a minimum requirement for applying the change theme?

    Correct Answer: A

    The minimum requirement for applying the change theme according to PRINCE2 is to identify whether an issue affects the continuation of the project. This encompasses the principle of continued business justification, which ensures that any identified issues are evaluated for their potential impact on the project's viability.

Discussion
MehanOption: A

The purpose of the change theme is to identify, ASESS, and control any potential and approved changes to the project baselines. A is Corretct

NugiOption: A

Definitely A. Reference: To be following PRINCE2, a project must, as a minimum: ● define its change control approach. This approach must minimally cover: ● how issues are identified and managed ● assessing whether identified issues might have a material impact on the business justification of the project (PRINCE2’s continued business justification principle)

Mehan

The purpose of the change theme is to identify, ASESS, and control any potential and approved changes to the project baselines.

JimethOption: A

It's A

KianaOption: A

Definitely B is the wrong answer it’s A

costin31Option: A

It is A!