Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 22

The project is approaching the end of stage 4 and all work will be completed as planned. The project manager is now preparing a plan for acceptance and the handover of the 'capability to provide health and safety training'.

Is this appropriate, and why?

    Correct Answer: C

    Closure activities should have been planned at the end of stage 3, not at the end of stage 4. This is to ensure that the project is well-prepared for the closure phase and that all necessary tasks and responsibilities are clearly defined and allocated beforehand. Planning the closure activities during stage 4 is too late and would not align with proper project management practices.

Discussion
pollonOption: C

C - Closing a project is part of the final stage i.e. Stage 4. All plans must be produced in the previous management stage i.e Stage 3

ameyaenggOption: C

C is correct

PieroBeOption: C

During the Managing a Stage boundary process at the end of stage 3 all the activities (including those related to the project closure) shall have been planned (activity "Plan the next management stage").

HelgeFFMOption: C

it is C, see 19.4.1