Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?
Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?
The PRINCE2 principle 'Manage by exception' is applied when tolerances are set to establish limits of authority and accountability. This principle is about setting tolerances for each project objective (time, cost, quality, scope, risk, and benefits) to manage the project by exception. If these tolerances are exceeded, the matter is escalated to the next level of management for a decision, thereby ensuring proper governance and control.
for me also B sounds like the right answer.
B sounds better