Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 160

Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?

    Correct Answer: C

    The PRINCE2 principle 'Manage by exception' is applied when tolerances are set to establish limits of authority and accountability. This principle is about setting tolerances for each project objective (time, cost, quality, scope, risk, and benefits) to manage the project by exception. If these tolerances are exceeded, the matter is escalated to the next level of management for a decision, thereby ensuring proper governance and control.

Discussion
HelgeFFMOption: B

for me also B sounds like the right answer.

MrMayOption: B

B sounds better