Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 179

DRAG DROP -

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Using the Project Scenario answer the following question. The Plan for stage 3 has been approved and work has commenced.

Column 1 contains a number of issues for this project. Select from Column 2 the appropriate category for each issue. Each selection from Column 2 can be used once, more than once or not at all.

Drop down the right answer from column 1 to column 2.

Hot Area:

    Correct Answer:

Discussion
ravi_aws

Transfer, Share, reduce, accept, fallback, reduce

ravi_aws

All answers are correct