Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 238

Which role should identify whether a project's management products need to be tailored?

    Correct Answer: D

    The Project Manager is responsible for tailoring management products to suit the specific needs of the project. This involves making decisions on how the project's processes, products, and themes will be adjusted to fit its size, complexity, and risk level. The Project Manager ensures the project management approach is appropriate and effective for the particular circumstances of the project.

Discussion
[Removed]Option: D

It should be D: Tailoring requires the project board and the project manager to make proactive choices and decisions on how PRINCE2 will be applied. 3.7

LynlOption: D

Answer should be D

bes_iOption: D

D. Project Manager The Project Manager is responsible for tailoring PRINCE2 to suit the specific needs of the project. This includes determining how the management products, processes, and themes will be adjusted to fit the project's size, complexity, and risk level. The Project Manager ensures that the project management approach is appropriate and effective for the particular circumstances of the project.

KANDUUR

Not sure that this is a correct answer.