Question 41

Which role is responsible for providing the customer's quality expectations and acceptance criteria for the project?

    Correct Answer: C

    In project management, the Senior User is typically responsible for specifying the needs of those who will use the final product, service, or result of the project. This includes providing the customer's quality expectations and acceptance criteria for the project. The Senior User ensures that the project will deliver a product that meets these requirements.

Discussion
PieroBeOption: C

Table 8.1

timedout

Table 8.1