The project manager is developing the stage 3 plan. The project manager is concerned that lots of new team members will join the project in stage 3. This risk to delivery has been recorded in the risk register. As a result, the stage 3 plan has been saved as a `draft` until this risk has been assessed. The project manager discusses the risk with project assurance before deciding what to do.
Is this an appropriate application of the 'plans' theme, and why?