The Finance Director has been appointed as the executive of the Health and Safety Training Project. She likes to be involved personally in all projects and authorize all large contracts. She has therefore asked the project manager to provide daily updates on project progress so that she can make decisions throughout each stage.
Is this an appropriate action, and why?