Question 43

PRINCE2 proposes 3 levels of Plan, which are they?

    Correct Answer: D

    PRINCE2 identifies three levels of plan: Project Plans, which address project-wide planning; Stage Plans, which provide detailed planning for each stage of the project; and Team Plans, which cover the work packages allocated to the teams. These levels ensure that planning is appropriate to the scale and scope at each layer of the project.

Discussion
timedoutOption: B

Notice is said "level", Stage and Exception are at the same level.

ManikRoy

Exception plan can be of all 3 levels.

mcesarlaraOption: D

9.2 En PRINCE2 hay tres niveles de plan: proyecto, fase y equipo.

GicaOption: D

D is correct: In PRINCE2, there are three levels of plan: project,stage and team. ( page 97)

Stu_DentOption: B

B is correct. Ref: 9.2 (page 97).