PRINCE2-Practitioner Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Exam - Question 241


A work package has been authorized by the project manager for the 'classroom-based training materials' and the 'accredited classroom-based course'. The course developer (team manager) has provided an exception report to the Senior Supplier stating that the time tolerance for the work package will be exceeded and this will cause the stage 2 plan to go into exception. The Senior Supplier has instructed the course developer to produce an exception plan.

Is this an appropriate application of the 'controlling a stage process', and why?

Show Answer
Correct Answer: D

The course developer should have raised the issue with the project manager as part of the 'execute a work package' activity. According to the principles of project management, issues within a work package should be reported to the project manager directly, who then decides on the necessary actions such as escalating to the Senior Supplier or other stakeholders if needed. This ensures that the project manager can maintain control over the stage process and adequately manage exceptions.

Discussion

1 comment
Sign in to comment
ravi_awsOption: D
Oct 7, 2023

No, because the course developer should have raised the issue with the project manager as part of the 'execute a work package' activity