PRINCE2-Foundation Exam QuestionsBrowse all questions from this exam

PRINCE2-Foundation Exam - Question 68


What product defines the reporting requirements between the Project Manager and Team Manager?

Show Answer
Correct Answer: D

The Work Package defines the reporting requirements between the Project Manager and Team Manager. It includes the description of the work, the product descriptions, the details of any constraints on production, and the confirmation of this agreement. The Work Package ensures that both the Project Manager and the Team Manager are aligned on the scope, deliverables, and reporting structure, facilitating clear communication and accountability.

Discussion

1 comment
Sign in to comment
omandeOption: D
Oct 21, 2023

Glossary: The work package will contain a description of the work, the product description(s), details of any constraints on production, and confirmation of the agreement between the project manager and the person or team manager who is to implement the work package that the work can be done within the constraints.