PRINCE2-Practitioner Exam - Question 237


DRAG DROP -

DIRECTING A PROJECT -

Here are three actions taken during the 'directing a project' process.

Which role (A-F) is responsible for each action?

Choose only ONE role for each action. Each role may be used once, more than once, or not at all.

Select and Place:

Show Answer
Correct Answer:

Discussion

1 comment
Sign in to comment
ravi_aws
Oct 6, 2023

Exec, senior user, senior user