Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 41

From whom does a Team Manager obtain approval for a completed product?

    Correct Answer: C

    A Team Manager obtains approval for a completed product from the authority defined in the Product Description. The Product Description specifies the people or skills required to produce, review, and approve the product. This ensures the product meets its quality criteria and the appropriate authority provides the necessary approval.

Discussion
Martin77Option: C

C is correct : obtaining approval for completed products from the authorities identified in the product description reference prince2 book - 18.3

ejaymacOption: A

I thought was the Project manager

JimethOption: C

Appendix A 17.1 - Product description ..."define the people or skills required to produce, review and approve the product" Answer is C

[Removed]Option: C

C is correct: The team manager ensures that products are created and delivered by the team to the project by: ● accepting and checking authorized work packages from the project manager ● ensuring that interfaces identified in the work package are maintained ● creating a team plan for the work packages being assigned (this may be done in parallel with the project manager creating the stage plan for the management stage) ● ensuring that the products are developed in accordance with any development method(s) specified in the work package ● demonstrating that each product meets its quality criteria through the quality method(s) specified in the product description; this may include using the PRINCE2 quality review technique (see Chapter 8) ● obtaining approval for completed products from the authorities identified in the product description ● delivering the products to the project manager in accordance with any procedures specified in the work package.

peppeOption: C

C is correct

JasonbahrOption: C

C is correct