Which is NOT considered when defining risk tolerance?

Show Answer
Correct Answer: B

When defining risk tolerance, considerations typically include the attitude towards risk-taking, the risk appetite of an organization, and the amount of risk deemed acceptable. The allocated risk budget, however, is more related to financial planning and resource allocation rather than the qualitative assessment of risk tolerance itself.

Discussion

4 comments
Sign in to comment
hatachino1Option: D
Sep 13, 2021

The correct answer must be D - The amount of risk a Project Board consider acceptable = risk tolerance

tsangckl
Jun 11, 2022

NOT...... ans is B

mazzantiemanueleOption: B
Mar 21, 2022

hatachino1: Note that the question is asking "Which is NOT considered when defining risk tolerance". The should be B, The allocated risk budget

skshah47Option: D
Mar 10, 2023

The concept of "personal preference" is generally not considered when defining risk tolerance in PRINCE2. The definition of risk tolerance should be based on objective factors related to the project and the organization, rather than personal preferences or biases. Therefore, option D "The amount of risk a Project Board considers acceptable" is not considered when defining risk tolerance.

AC_DoraOption: B
Mar 23, 2024

The correct answer should be B. Risk tolerance is related to the acceptance of the outcomes of a risk should they occur, and having the right resources and controls in place to absorb or “tolerate” the given risk.