Question 266

The Health and Safety Training Project is following ABC Company's standard course development model. This model requires that the project initiation documentation (PID) should include an additional section that shows how different learning styles will be accommodated in the classroom-based and e-learning courses. The executive has agreed that this section should be included in this project's PID.

Is this an appropriate application of the 'tailor to suit the project' principle, and why?

    Correct Answer: B

    The PRINCE2 framework encourages tailoring to suit the specific needs of a project. The PID (Project Initiation Documentation) serves as a foundational document that outlines various aspects of how the project will be managed and executed, including any customization of the standard processes and methodologies to better fit the unique requirements of the project. Including a section to accommodate different learning styles in classroom-based and e-learning courses demonstrates how PRINCE2 is being tailored to meet the specific needs of the Health and Safety Training Project, making this an appropriate application of the 'tailor to suit the project' principle.

Discussion
ravi_awsOption: A

Yes, because management products should be tailored to ensure PRINCE2 is used appropriately

ravi_aws

Sorry, The answer is B. Yes, because the PID should describe how PRINCE2 has been tailored to meet the needs of a particular project.